Owner's side is finished!

The owner's side of this duplex has been completed, and they have started moving in!

|

Paint, carpet & vinyl.

The owner's side of this duplex is almost finished. The second floor is complete, painted & carpeted. The first floor is painted and the kitchen vinyl floor installed. Only a few more weeks until this family can come home!


|

The sheetrock is in.

This house has come a long way and is starting to shape up. The sheet rock is installed and ready for paint. The heating system is installed.



|

Subflooring & plumbing in.

The petitions are in and the sub-flooring is in. The shower units are installed and the plumbing is being installed by Progressive Mechanical. The walls were treated for smoke with Pro-block...

|

Level flooring, installation of support beams.

We have leveled the flooring and strapped the ceiling...

|

More exterior.

More exterior work including house wrap, window trim & siding.



|

Interior work begins.

Join Rick for a walk-through of the building as he reveals the status of the interior and points out some of the work that needs to be done.

|

Removed porch, reduced window openings.

The new hip-on-hip roof has been shingled, thanks to DME Construction.

We also removed the front porch and reduced the window openings.

|

Roof completed, exterior work.

Rick discusses exterior plans for the building. The new hip-on-hip roof has been installed. What an awesome job by DME Construction!


|

New roof installation.

DME Construction begins installation of new roof.


|

Fire Restoration begins.

Rick Bagley Contracting, LLP begins a new project restoring a home that was severely damaged by fire. The upper floors were badly damaged leaving a hole in the roof. We had to completely remove the roof on this house.

|